Status Reports (ending 10/30/1996)

Jason I. Hong (hong@cc.gatech.edu)
Wed, 30 Oct 1996 11:42:55 -0500 (EST)

Cyberguide group status report
==============================

Date: 10/23/1996 - 10/30/1996

Missing Timesheets
==================

Marty
Ed

Time Categories (leave blank if 0)
==================================

1. Meetings, Preparation - 4
2. Meetings, Attend - 8
3. Presentations, Preparation - 1
4. Presentations, Do -
5. Research, PC - 3
6. Research, Sun -
7. Doc, Plan -
8. Doc, Design -
9. Doc, Test Plan -
10. Doc, Analysis - 2.5
11. Doc, Test Results -
12. Doc, Final -
13. Code, Basic-PC - 10
14. Code, Basic-Sun -
15. Code, Communications-PC -
16. Code, Communications-Sun -
17. Web - 2
18. Equipment - 2
19. Backup -
20. Video -
21. Hardware -
22. Unclassified task (specify) -
Requirements doc - 4

Total: pending

Primary goals accomplished this week
====================================

o Finished TIGER Data Analysis.
o Finished TIGER data analysis document.
o Started requirements doc
o Began prototyping initial data classes.
o Finished web research, no free PC based Tiger/Line code was found

Primary goals not accomplished this week
========================================

o Did not get autocad format map of GaTech campus from publications office
( forgot and low priority )

Primary goals for next week (in order of priority)
==================================================

o Work on requirements associated with data.
o Work with group to produce/finalize requirements for customer approval
o Brainstorm possible data structures to use with the TIGER/Line database
o Work on the design and implementation of data classes.
o See if we can get access to 1994 TIGER/Line data from our library
o Start on design doc

Notes and comments
==================

--------------------------------------------------------------------------------

Cyberguide individual status report
===================================

Name: Chris Reynolds
Date: 10/29/1996

Time Categories (leave blank if 0)
==================================

1. Meetings, Preparation - 2
2. Meetings, Attend - 2
5. Research, PC - 3
17. Web - 2

Specified goals accomplished this week (in order of priority)
=============================================================

* Started looking into possible requirements.
* Jeff produced a "proof of concept" prototype that we will be
using to help brainstorm ideas.
* Finished web research, no free PC based Tiger/Line code
was found. (Have not been able to download new 1994 data).

Specified goals not accomplished this week (in order of priority and reason)
============================================================================

* None.

Goals for next week (in order of priority)?
===========================================

* Work with Jeff to brainstorm possible data structures to
use with the Tiger/Line database.
* Work with group to produce/finalize requirements for
customer approval.

Notes and comments
==================

--------------------------------------------------------------------------------

Cyberguide individual status report
===================================

Name: Jason Hong
Date: 10/30/1996

Time Categories (leave blank if 0)
==================================

1. Meetings, Preparation - 2
2. Meetings, Attend - 2
3. Presentations, Preparation -
4. Presentations, Do -
5. Research, PC -
6. Research, Sun -
7. Doc, Plan -
8. Doc, Design -
9. Doc, Test Plan -
10. Doc, Analysis - 0.5
11. Doc, Test Results -
12. Doc, Final -
13. Code, Basic-PC -
14. Code, Basic-Sun -
15. Code, Communications-PC -
16. Code, Communications-Sun -
17. Web -
18. Equipment -
19. Backup -
20. Video -
21. Hardware -
22. Unclassified task (specify) -
Requirements doc - 4

Specified goals accomplished this week (in order of priority)
=============================================================

Started requirements doc
Got PC software connectivity for QuickTake 100 from Kirk (via e-mail)

Specified goals not accomplished this week (in order of priority and reason)
============================================================================

Did not get autocad format map of GaTech campus from publications office
( forgot and low priority )

Goals for next week (in order of priority)?
===========================================

Complete requirements doc
Start on design doc
See if we can get access to 1994 TIGER/Line data from our library
Get CGI script for timesheets online
Get PC software connectivity installation disks from Kirk

Notes and comments
==================

--------------------------------------------------------------------------------

Cyberguide individual status report
===================================

Name: Jeff Dempsey
Date: 10/29/96

Time Categories (leave blank if 0)
==================================

1. Meetings, Preparation -
2. Meetings, Attend - 2
3. Presentations, Preparation -
4. Presentations, Do -
5. Research, PC -
6. Research, Sun -
7. Doc, Plan -
8. Doc, Design -
9. Doc, Test Plan -
10. Doc, Analysis - 2
11. Doc, Test Results -
12. Doc, Final -
13. Code, Basic-PC - 10
14. Code, Basic-Sun -
15. Code, Communications-PC -
16. Code, Communications-Sun -
17. Web -
18. Equipment -
19. Backup -
20. Video -
21. Hardware -
22. Unclassified task (specify) -

Specified goals accomplished this week (in order of priority)
=============================================================
Finished TIGER Data Analysis.
Finished TIGER data analysis document.
Began prototyping initial data classes.

Specified goals not accomplished this week (in order of priority and reason)
============================================================================

Goals for next week (in order of priority)?
===========================================
Work on requirements associated with data.
Work on the design and implementation of data classes.

Notes and comments
==================

--------------------------------------------------------------------------------

Cyberguide individual status report
===================================

Name: Shervin Dana
Date: Oct/29/96

Time Categories (leave blank if 0)
==================================

1. Meetings, Preparation -
2. Meetings, Attend - 2
3. Presentations, Preparation - 1
4. Presentations, Do -
5. Research, PC -
6. Research, Sun -
7. Doc, Plan -
8. Doc, Design -
9. Doc, Test Plan -
10. Doc, Analysis -
11. Doc, Test Results -
12. Doc, Final -
13. Code, Basic-PC -
14. Code, Basic-Sun -
15. Code, Communications-PC -
16. Code, Communications-Sun -
17. Web -
18. Equipment - 2
19. Backup -
20. Video -
21. Hardware -
22. Unclassified task (specify) -



Specified goals accomplished this week (in order of priority)
=============================================================




Specified goals not accomplished this week (in order of priority and reason)
============================================================================

Goals for next week (in order of priority)?
===========================================
Get together with Dale Everrete to find out what equipment are
availabe in FCE.


Notes and comments
==================

--------------------------------------------------------------------------------

-- 
Fortune favors the prepared mind
   - Louis Pasteur

- Jason I. Hong (hong@cc.gatech.edu)