Project Schedule

Winter Quarter 1996
1/19/96

Document Author:

Joel Furnsinn

Project Sponsors:

GregoryAbowd
Ian Smith

The Just Another Version of Anarchy Team:

Brice Wilson (Manager/Programmer)
Jay Bredenberg (Architect)
Aaron Sims (Manager/Architect)
John Stevens (Programmer)
Joel Furnsinn (Technical Writer)


The Current Schedule

Last Modified (2/8/96)

ACTIVITIES
Requirements 10 15
Planning 4 6 6 6 6 6 6 6
Training 13 16 16
Writing 6 6 4 8 8 8 4 4
Design 4 12 12 12
Coding 16 16 16
Debug 20 20 10
Revising 15 15
Meetings 20 25 25 25 25 25 25 25
TIME -1/15- -1/22- -1/29- -2/5- -2/12- -2/19- -2/26- -3/4-
Milestones 1/19 Project Plan 1/29 Requirements Document 2/9 Design Document 2/23 Initial Prototype 3/6 Final Project


The Schedule as of 1/31/96

ACTIVITIES
Requirements 15 15
Planning 6 6 6 6 6 6 6 6
Training 16 16 16
Writing 4 4 4 8 8 8 4 4
Design 12 12 12
Coding 16 16 16
Debug 20 20 10
Revising 15 15
Meetings 25 25 25 25 25 25 25 25
TIME -1/15- -1/22- -1/29- -2/5- -2/12- -2/19- -2/26- -3/4-
Milestones 1/19 Project Plan 1/29 Requirements Document 2/9 Design Document 2/23 Initial Prototype 3/6 Final Project


The Schedule as of 2/16/96

ACTIVITIES
Requirements 15 15
Planning 6 6 6 3 3 3 3 3
Training 16 16 16
Writing 4 4 4 8 8 8 4 4
Design 12 25
Coding 15 25 30
Debug 10 10 10
Revising 5 5
Meetings 25 25 25 10 10 10 10 10
TIME -1/15- -1/22- -1/29- -2/5- -2/12- -2/19- -2/26- -3/4-
Milestones 1/19 Project Plan 1/29 Requirements Document 2/9 Design Document 2/23 Initial Prototype 3/6 Final Project


The Schedule as of 3/6/96

ACTIVITIES
Requirements 15 15
Planning 6 6 6 3 3 3 6 6
Training 16 16 16
Writing 4 4 4 8 8 8 4 10
Design 12 25
Coding 15 25 30
Debug 10 10 10
Revising 5 15
Meetings 25 25 25 10 10 10 10 10
TIME -1/15- -1/22- -1/29- -2/5- -2/12- -2/19- -2/26- -3/4-
Milestones 1/19 Project Plan 1/29 Requirements Document 2/9 Design Document 2/23 Initial Prototype 3/6 Final Project

Link to the Java Mail Reader Project Notebook
Last Modified 2/8/96 -- Joel Furnsinn