Course: CS3302 (Spring 1996)
| Instant Finance Group | |
| Name | Title |
| Brian Leslie | Manager |
| Dedrick Duckett | Architect |
| David Daniel | Technical Writer |
| Geoff Menegay | Programmer |
| Jason Pastor | Programmer |
| ACTIVITIES | hours per week | Planned Total | Actual Total | ||||||||
| Meetings | 7 | 10 | 8 | 10 | 5 | 5 | 7 | 12 | 7 | 68 | 71 |
| Requirements | 5 | 2 | 15 | 2 | 6 | 25 | 30 | ||||
| Documentation | 5 | 7 | 18 | 10 | 13 | 5 | 15 | 10 | 15 | 73 | 98 |
| Training | 40 | 15 | 18 | 5 | 7 | 9 | 50 | 94 | |||
| Preliminary Design / Prototyping |
5 | 17 | 3 | 3 | 5 | 6 | 25 | 39 | |||
| Detailed Design | 5 | 10 | 6 | 25 | 21 | ||||||
| Coding | 15 | 2 | 10 | 30 | 15 | 20 | 70 | 92 | |||
| Pre-Integration Testing |
.5 | 8 | 8 | 25 | 16.5 | ||||||
| Integration | 1 | 10 | 20 | 35 | 31 | ||||||
| Post-Integration Testing |
10 | 10 | 5 | 100 | 25 | ||||||
| Modification / Enhancements |
2 | 30 | 2 | ||||||||
| MILESTONES | Project Teams | Project Plan | Requirements Document |
Design Document | Final Demo | Project Notebook | |||||
| Apr. 3 | Apr. 8 | Apr. 22 | May 6 | May 20-22 | May 29 | ||||||
| DATE | April | May | |||||||||
| 1 - 7 | 8 - 14 | 15 - 21 | 22 - 28 | 29 - 5 | 6 - 12 | 13 - 19 | 20 - 26 | 27 - 2 | |||
| Planned Totals | 62 | 62 | 62 | 70 | 62 | 67 | 62 | 57 | 22 | 526 | |
| Actual Totals | 62 | 71.5 | 64 | 40 | 84 | 57 | 62 | 52 | 27 | 519.5 | |